2024 Street Resurfacing Project

Overview

The Town of Carrboro maintains 48.04 miles of roadways comprising of 566 street segments or blocks, 41 miles of sidewalks, and 872 curb ramps throughout the community. The 2024 Street Resurfacing Project is intended to keep streets and curb ramps safe and in good condition for all users, and to make improvements strategically and efficiently to ensure safer and longer-lasting streets and curbs.

Project Description

Carrboro’s 2024 Street Resurfacing Project includes improvements to 20,780 linear feet of roadways and 1,285 linear feet of greenways.  Work includes asphalt rejuvenation, pavement milling, full depth patching, and related construction activity such as curb ramp improvements, manhole adjustments and pavement markings.  

The initial phase of the project includes upgrading sidewalk ramps to comply with ADA standards and repairing the current curb and gutter. The second phase targets pavement rejuvenation to extend the lifespan of treated surfaces, reduce overall life-cycle costs of paved roads, mitigate urban heat islands, and decrease pollution. The final phase will concentrate on street resurfacing.

Pavement Rejuvenation

Pavement Rejuvenation uses titanium dioxide additive shown to reduce urban heat islands and pollution.  To learn more visit Pavement Technology, Inc., or view PlusTi Brochure

Note: Roadways may be traveled on after the titanium dioxide additive has been applied.  Pets should be kept off treated roadways until  they have completely dried, approximately 24 hours.  

Ti Pollution Capture: Smog Eating Technology

Project Timeline (Weather Permitting)

  1. Concrete Work:
    • Start Date: Friday, August 28th
    • End Date: Friday, August 30th
  2. Pavement Rejuvenation:
    • Start Date: Wednesday, August 27th
    • End Date: Friday, August 29th
  3. Street Resurfacing: 
    • Start Date: To be determined. Begins with grinding off the surface of the existing asphalt

Notifications

NO PARKING signs will be posted in advance on streets directly affected by the project. Notices will be placed on cars as necessary.

  1. Project Maps
  2. Project Improvement List

2024 Street Resurfacing Project  Maps

2024 Street Resurfacing Project Maps (PDF)

During Resurfacing

  1. Please observe all signage and flaggers.
  2. Be aware of all workers and equipment in the street and please drive slowly and carefully. 
  3. Please do not park on street until work is complete and your entire road has been paved and stripped. If you cannot avoid parking, on the street please be prepared to move your vehicle upon request when work is being performed on your street.  
  4. Please keep yard debris out of street/curb.  

Residents and motorists may be inconvenienced by the project work. We apologize for any inconvenience and appreciate your patience and cooperation during the period of improvement.

Questions

If you have any questions related to the project, please contact Public Works Department at (919) 918-7425 or email pworks@carrboronc.gov